How much MOT Type 1 you actually need

Type 1 is sold by the tonne and laid by the millimetre, and it loses about a fifth of its volume under a wacker. Most calculators handle that badly — several apply the compaction allowance twice and sell you a quarter more stone than the job needs. This applies it once, and shows the arithmetic.

Sub-base for drives, patios, paths and sheds. Enter the area and the finished compacted depth, and get the tonnage to order.

Works in metric and US imperial — you choose at the start and can switch at any time. Every figure this calculator uses is published with its source, and the result comes with a printable order sheet. No account, no email, and nothing you type leaves your browser.

Related: Paver base calculator · Gravel calculator · Concrete calculator

All calculators · How to use them · The standards behind our figures

How the sum works

Type 1 is sold by the tonne and laid by the millimetre, and it loses about a fifth to a quarter of its volume under a wacker. Enter the area and the finished compacted depth; the calculator adds the compaction allowance once and converts at 1,680 kg/m³. Several calculators apply that allowance twice, which is why their answers come out high — order the loose figure here and add nothing to it.

A worked example

A 5 × 4 m patio sub-base at 100 mm finished is 2 m³ compacted, so about 2.5 m³ loose, weighing roughly 4.2 tonnes. Now the trap: in bulk bags at a declared minimum fill of 800 kg, that is six bags, not four. Bags are where Type 1 jobs go wrong on quantity more than anywhere else.

What Type 1 actually is

Not a trade nickname — a specification. SHW Series 800 Clause 803 requires the mixture to meet BS EN 13285 and Table 8/1, with the grading summarised in Table 8/6a: 63 mm at 100%, 31.5 mm at 75–99%, 16 mm at 43–81%. That grading is why it locks up so hard: there is a continuous spread of particle sizes with fines to fill the gaps. The clause itself is set out here.

Questions people actually ask

How many tonnes of MOT Type 1 do I need?

Multiply area by the finished compacted depth, add about 25% for compaction, then multiply by 1.68 to get tonnes. A 5 by 4 m patio at 100 mm finished works out at roughly 4.2 tonnes. This calculator applies the allowance once, so use the figure it gives without adding to it.

Is a tonne bag of Type 1 really a tonne?

No, and there are two different bags. A bag sold by volume holds about 750 litres; one sold by weight carries a minimum declared fill of 800 kg. Either way you get noticeably less than a tonne, so convert your tonnage into bags rather than assuming one bag equals one tonne.

What is the difference between Type 1 and Type 3?

Type 3 (Clause 805) is the reduced-fines version, made for permeable builds. It drains where Type 1 does not, which is what SuDS and permeable paving require — but it is less stable underfoot and slightly lighter, so the tonnage differs.

Can I use scalpings instead of Type 1?

Sometimes. Scalpings are cheaper and less consistent: quarry by-product rather than a specified grading, so they vary between loads and between quarries. Fine as a capping layer or under a shed, but not where a specified sub-base is called for.